Jun. 16, 2025
Hydropower, or hydroelectric power, is one of the oldest and largest sources of renewable energy, which uses the natural flow of moving water to generate electricity. Hydropower currently accounts for 27% of total U.S. utility-scale renewable electricity generation and 5.86% of total U.S. utility-scale electricity generation.
You will get efficient and thoughtful service from IWHR.
While most people might associate the energy source with the Hoover Dam—a huge facility harnessing the power of an entire river behind its wall—hydropower facilities come in all sizes. Some may be very large, but they can be tiny, too, taking advantage of water flows in municipal water facilities or irrigation ditches. They can even be “damless,” with diversions or run-of-river facilities that channel part of a stream through a powerhouse before the water rejoins the main river. Whatever the method, hydropower is much easier to obtain and more widely used than most people realize. In fact, all but two states (Delaware and Mississippi) use hydropower for electricity, some more than others. For example, in about 60% of the state of Washington’s electricity came from hydropower.
In a study led by the National Renewable Energy Laboratory on hydropower flexibility, preliminary analysis found that the firm capacity associated with U.S. hydropower’s flexibility is estimated to be over 24 GW. To replace this capability with storage would require the buildout of 24 GW of 10-hour storage—more than all the existing storage in the United States today.
Hydropower is an affordable source of electricity that costs less than most. Since hydropower relies only on the energy from moving water, states that get the majority of their electricity from hydropower, like Idaho, Washington, and Oregon, have lower energy bills than the rest of the country.
Compared to other electricity sources, hydropower also has relatively low costs throughout the duration of a full project lifetime in terms of maintenance, operations, and fuel. Like any major energy source, significant upfront costs are unavoidable, but hydropower’s longer lifespan spreads these costs out over time. Additionally, the equipment used at hydropower facilities often operates for longer periods of time without needing replacements or repairs, saving money in the long term.
The installation costs for large hydropower facilities consist mostly of civil construction works (such as the building of the dams, tunnels, and other necessary infrastructure) and electromechanical equipment costs (electricity-generating machinery). Since hydropower is a site-specific technology, these costs can be minimized at the planning stage through proper selection of location and design.
The benefits of hydropower have been recognized and harnessed for thousands of years. In addition to being a renewable and cost-effective form of energy, hydropower plants can provide power to the grid immediately, serving as a flexible and reliable form of backup power during major electricity outages or disruptions. Hydropower also produces a number of benefits outside of electricity generation, such as flood control, irrigation support, and water supply.
The history of hydropower dates back thousands of years. For example, the Greeks used water wheels to grind wheat into flour more than 2,000 years ago. The evolution of the modern hydropower turbine began in the mid-s when a French hydraulic and military engineer, Bernard Forest de Bélidor, wrote Architecture Hydraulique. Many key developments in hydropower technology occurred during the first half of the 19th century, and more recently, the past century has seen a number of hydroelectric advancements that have helped hydropower become an integral part of the renewable energy mix in the United States.
If you mean energy (which is what you sell), read How much energy could I generate from a hydro turbine?.
If you mean power, read on.
Power is the rate of producing energy. Power is measured in Watts (W) or kiloWatts (kW). Energy is what is used to do work and is measured in kilowatt-hours (kWh) or megawatt-hours (MWh).
In simple terms, the maximum hydropower power output is entirely dependent on how much head and flow is available at the site, so a tiny micro-hydro system might produce just 2 kW, whereas a large utility-scale hydro system could easily produce hundreds of Megawatts (MW). To put this in context, a 2 kW hydropower system could satisfy the annual electrical energy needs of two average UK homes, whereas a utility-scale 200 MW system could supply 200,000 average UK homes.
If you don’t mind equations the easiest way to explain how much power you could generate is to look at the equation for calculating hydropower:
P = m x g x Hnet x η0.85 x 0.95 x 0.93 = 0.751 i.e. 75.1%
Therefore, if you had a relatively low gross head of 2.5 metres, and a turbine that could take a maximum flow rate of 3 m3/s, the maximum power output of the system would be:First convert the gross head into the net head by multiplying it by 0.9, so:
Hnet = Hgross x 0.9 = 2.5 x 0.9 = 2.25 mThen convert the flow rate in m3/s into litres/second by multiplying it by , so:
3 m3/s = 3,000 litres per secondRemember that 1 litre of water weighs 1 kg, so m is the same numerically as the flow rate in litres/second, in this case 3,000 kg/s.
Now you are ready to calculate the hydropower power: Power (W) = m x g x Hnet x η = 3,000 x 9.81 x 2.25 x 0.751 = 49,729 W = 49.7 kWNow, do the same for a high-head hydropower site where the gross head is 50 metres and maximum flow rate through the turbine is 150 litres / second.
In this case Hnet = 50 x 0.9 = 45 m and the flow rate in litres/second is 150, hence:
Power (W) = m x g x Hnet x η = 150 x 9.81 x 45 x 0.751 = 49,729 W = 49.7 kWWhat is interesting here is that for two entirely different sites, one with a net head of 2.25 metres and the other 45 metres, can generate exactly the same amount of power because the low-head site has much more flow (3,000 litres / second) compared to the high-head site with just 150 litres/second.
This clearly shows how the two main variables when calculating hydropower power output from a hydropower system are the head and the flow, and the power output is proportional to the head multiplied by the flow.
Of course the two systems in the example above would be physically very different. The low head site would need a physically large Archimedean Screw or Kaplan turbine inside a turbine house the size of a large garage because it would have to be physically large to discharge such a large volume of water with a relatively low pressure (head) across it. The high-head site would only need a small Pelton or Turgo turbine the size of a fridge because it only has to discharge 5% of the flow rate of the low-head system and under a much higher pressure.
It is interesting that in the real world the heads and flows in the example above aren’t too far from reality, because high-head sites tend to be at the heads of rivers in upland areas, so the ground slopes steeply enabling high heads to be created, but the rainfall catchment of the watercourse is relatively small, so the flow rate is small. That same upland stream 20 km downstream would have merged with countless small tributaries and formed into a much larger river with a higher flow rate, but the surrounding area would now be lowland agricultural land with only a modest gradient. It would only be possible to have a low head across a weir to avoid risking flooding the surrounding land, but the flow rate in the lowland river would be much larger to compensate.
The UK has a range of all types of high, medium and low head hydropower sites. England has more low-head sites, Scotland more high-head, and Wales a mixture of everything but still with significant medium and high-head opportunities.
Power and energy generation can be maximised by keeping the inlet screen clear of debris which maintains a maximum system head. This can be automatically acheived using our innovative GoFlo Travelling screen manufactured in the UK by our sister company . Discover the benefits of installing a GoFlo travelling screen on your hydropower system in this case study: Maximising the benefits of hydropower technology using innovative GoFlo travelling screen technology.
If you mean power, read How much power could I generate from a hydro turbine?
If you mean hydro energy (which is what you sell), read on.
Energy is everything; you can sell energy, but you can’t sell power (at least not in the context of small hydropower). People often get obsessed with wanting the highest possible power output from a hydro system, but this is really quite irrelevant.
When you sell electricity you are paid depending on the number of kWh (kilowatt-hours) you sell (i.e. based on the energy) and not for the power you produce. Energy is the capacity to do work, while power is the rate at which work can be done. It is a bit like miles and miles-per-hour; the two are clearly related, but are fundamentally different.
If you want a quick answer to the question, see the table below which shows how much hydro energy would be generated in a year for a range of hydro systems with different maximum power outputs. It is interesting to note that an ‘average’ UK home uses 12 kWh of electricity every day, or 4,368 kWh per year. Hence the number of ‘average UK homes powered’ is also shown homes powered’ is also shown. There is a more detailed discussion below for anyone that is interested.
Maximum Power Output Annual Energy Production [AEP] No. of ‘Average’ UK Homes Powered 5 kW 22 MWh 5 25 kW 110 MWh 25 50 kW 219 MWh 50 100 kW 438 MWh 100 250 kW 1,095 MWh 250 500 kW 2,190 MWh 500For any hydropower site, once all of that site’s peculiarities have been considered and the ‘Hands Off Flow (HOF)’ agreed with the environmental regulator, there will normally be a single optimum turbine choice that will make best use of the water resource available and result in the maximum energy production. Maximising hydro energy production within the project budget available is one of the key skills of a hydropower engineer.
To estimate how much energy a hydropower system produces accurately needs specialist software, but you can get a good approximation by using a ‘capacity factor’. A capacity factor is basically the annual amount of energy produced by a hydro system divided by the theoretical maximum if the system operated at maximum power output 24/7. For a typical UK site with a good quality turbine and a maximum flow rate of Qmean and a HOF of Q95, it can be shown that the capacity factor would be approximately 0.5. Assuming you know the maximum power output from the hydro system the Annual Energy Production (AEP) from the system can be calculated from:
Annual Energy Production (kWh) = Maximum power output (kW) x No. hours in a year x capacity factor
Note that there are 8,760 hours in a (non leap) year.
As an example, for the low-head and high-head example sites above, both of which had maximum power outputs of 49.7 kW, the Annual Hydro Energy Production (AEP) would be:
AEP = 49.7 (kW) X 8,760 (h) X 0.5 = 217,686 (kWh)
Energy generation can be maximised by keeping the inlet screen clear of debris which maintains a maximum system head. This can be automatically acheived using our innovative GoFlo Travelling screen manufactured in the UK by our sister company . Discover the benefits of installing a GoFlo travelling screen on your hydropower system in this case study: Maximising the benefits of hydropower technology using innovative GoFlo travelling screen technology.
This shows an annual average electricity price rise between and of approximately 9% per year.
Future changes to electricity prices may not follow historical price rises and are very hard to predict because they are heavily influenced by fossil-fuel prices and government policy changes in response to market conditions and carbon reduction commitments.
The last assessment of Energy Prices and Bills made by the Committee on Climate change was in , and their report is here. Their assessment of the impact of carbon reduction commitments made to how price rises of approximate 3% per year to as shown on the right. The UK government has since increased its commitment to carbon reduction which would mean that investment in low carbon energy will inevitably have to increase beyond that shown in this report.
It is very difficult to predict the future cost of energy, it could rise based on historical price rises, but is more likely to rise based on predictions made by authoritative bodies advising the government – so for the purposes of this illustration an annual electricity price rise of 3% is assumed, as opposed to the historical price rise of 9%.
For more information, please visit hydraulic dam companies.
For illustration purposes, the net income (annual effective gain from electricity production, minus typical operational and maintenance costs) for four scenarios are shown below, assuming a 40 year lifespan for the hydropower equipment:
Illustration 1 – 100% of the generated energy consumed on site, annual electricity price rise of 3%, hydro system generating at a typical UK capacity factor of 0.5, annual income averaged over 40 years. In this scenario the net income could be:
It’s quite difficult to make generalisations about the cost to build hydro systems because of the different combinations of head (the change in water levels between the intake and discharge) and maximum flow rate, and how that affects the maximum power output and choice of turbine type.
Also the extent of any civil engineering works is very site dependent, with some new-build sites requiring everything to be built from scratch, while other retrofit projects can make use of and adapt the existing civil engineering structures.
Having said that, we’ll try to answer the question anyway to give you an idea of the ‘scale’ of costs involved. The table below is a rough ball-park estimate of typical project costs for systems requiring an ‘average’ amount of civil engineering works and grid connection upgrades and assuming access to the site was reasonable. In all cases it is assumed that good quality hardware is used throughout, which we would recommend anyway if you want a reliable hydro system in the long-term.
It is possible to install systems for a lower cost, particularly if the existing infrastructure at the site lends itself to easy adaption for a modern hydropower system so only modest or no civil engineering works would be needed. However even in the most favourable circumstances it is unlikely that the cost would reduce by more than 50% from that shown in the table.
Maximum Power Output Estimated Project Cost £ / kW installed 25 kW £169k £6.8k 50 kW £300k £6.0k 100 kW £529k £5.3k 250 kW £963k £3.8k 500 kW £1.6M £3.2kTo estimate the cost to build hydro systems for a maximum power output between the bands shown, use the chart below and read-off the appropriate £/kW figure – for example a 130 kW hydro system would be approximately
130kW x 4,800 £/kW = £624,000.
Hydropower system build cost
The operating hydropower system cost varies depending on many factors, the main ones being the size of the system, the head and the type of turbine. If you want a quick idea of operational costs use the table below, or if you have a particular size of system you are interested in use the chart
Maximum Power Output Estimated Annual Operational Costs 5 kW £2,200 25 kW £4,000 50 kW £6,300 100 kW £11,000 250 kW £25,000 500 kW £48,300Generally speaking, hydropower systems are reliable in the long-term. The biggest maintenance task is keeping the intake screen clear of debris, particularly during the autumn period or after heavy rain. Even outside of these periods it is a surprising just how much debris there is in flowing water. Smaller hydro systems up to around 25 kW can have manually-raked intake screens, though many owners still opt for automatic screen cleaning systems, such as the travelling screens manufactured by our sister company, GoFlo Screens. Larger systems will invariably have automatically-raked systems or in the case of high-head sites a self-cleaning coanda intake screen is often used.
Archimedean screws are slightly different because they can operate with intake screens with a wide bar-spacing (up to 100 mm) which allows a lot of the small debris to pass straight through the system reducing the amount of screen cleaning required, though larger debris will still get caught on the screen and will need to be removed either manually or automatically.
It is also good practice to look-over a hydro site on a daily basis, or certainly a couple of times a week. This not only means that the intake screens will be checked, but would also give an early warning of any other issues before they become significant. Hydropower machinery is quite rugged and generally heavily built.
As hydro turbines are not subjected to shock loads like many other machines, they generally have very long operational lives of at least 40 years. Routine maintenance is monthly grease lubrication and hydraulic fluids are normally changed every two or three years. Drive belts (if fitted) normally last at least three years. Generator bearings should last 10 to 15 years and turbine bearings much longer because of the slower rotational speeds (on lower-head systems at least). As well as maintenance, the other hydropower system cost included in the estimates above are insurance and business rates. Business rates are a particularly complicated subject because they vary depending on where you are and the size of the system.
This shows an annual average electricity price rise between and of approximately 9% per year. Future changes to electricity prices may not follow historical price rises and are very hard to predict because they are heavily influenced by fossil-fuel prices and government policy changes in response to market conditions and carbon reduction commitments.
Committee on Climate Change Electricity Price predictions
The last assessment of Energy Prices and Bills made by the Committee on Climate change was in , and their report is here. Their assessment of the impact of carbon reduction commitments made to show price rises of approximately 3% per year to as shown on the right. The UK government has since increased its commitment to carbon reduction which would mean that investment in low carbon energy will inevitably have to increase beyond that shown in this report. Please note it is possible that electricity prices may rise or fall in the future.
For illustration purposes, the Rate of Return for three scenarios are shown below. This assumes a typical lifespan of 40 years for hydropower equipment – in reality this could be considerably longer if it is well maintained. The hydro system returns on investment shown are realistic for typical, viable sites:
The table below shows what the Internal Rate of Return (IRR) could be for a range of small hydro and micro hydro systems where 100% of electricity is consumed on site and there is an assumed annual price rise of the cost of electricity of 3%.
Hydro Return on Investment Maximum Power Output Internal Rate of Return (IRR) New Build Internal Rate of Return (IRR) Existing Site, No Civils 25 kW 10% 15% 50 kW 12% 17% 100 kW 12% 18% 250 kW 14% 20% 500 kW 17% 24%Unless the commercial operation is a 24 hour, high energy use operation, or energy storage is added, then it is likely that only a portion of electricity generated by the hydro system can offset on site electricity usage. If only a proportion of electricity can be consumed on-site, this scenario is complex and depends on electricity consumption and generation patterns over a period of time. Renewables First can assess this demand and generation relationship as part of the Hydropower Feasibility Study service. For illustrative purposes, we will assume that 50% of electricity generated is consumed on site, and 50% is exported to the grid.
The table below shows what the Internal Rate of Return (IRR) could be where 50% of electricity is consumed on site and there is an assumed annual price rise of the cost of electricity of 3%.
Hydro Return on Investment Maximum Power Output Internal Rate of Return (IRR) New Build Internal Rate of Return (IRR) Existing Site, No Civils 25 kW 7% 10% 50 kW 8% 12% 100 kW 9% 13% 250 kW 11% 15% 500 kW 13% 18%Finally, if it is not possible to consume any electricity on-site, then 100% of the electricity must be exported to the grid. A typical initial export price of 6.5 p/kWh, which increases annually by an inflation rate of 2%, is used for this Rate of Return illustration:
Hydro Return on Investment Maximum Power Output Internal Rate of Return (IRR) New Build Internal Rate of Return (IRR) Existing Site, No Civils 25 kW 2% 5% 50 kW 4% 6% 100 kW 5% 7% 250 kW 7% 10% 500 kW 8% 12%The IRR is calculated over 40 years, assuming good quality hardware is used and the system is well maintained. Options are given for new build projects including civils works and for existing sites with no or only minor civils works.
It is worth mentioning that sometimes intangible benefits can be worth a lot, for example at sites frequented by tourists a small hydro or micro hydro system can add a lot of additional interest as a visitor attraction and in other cases the marketing benefit to a company from being able to say that their energy is generated on site from zero emission hydropower can be significant.
The best sites are generally larger (100 kW+), with higher heads, easy to adapt infrastructure, easy access and a good grid connections.
One of the sources of income for hydro turbines was the Feed in Tariff (FiT) scheme. This scheme was scrapped at the end of March .
However, there are still several key sources of income for wind turbine projects that are significant and can make a project financially viable. They are:
This is payable for every kWh of electricity exported to the national grid. Exporting electricity means that it must pass outwards into the local electricity distribution network (what most people call ‘the grid’) through an export meter. An export meter looks the same as a normal import meter, but records the flow of electricity outwards from a site. Nowadays a single import/export meter is normally fitted.
To export all the energy produced by a hydro turbine it would have to be directly connected to the grid with its own dedicated electrical supply and not first pass through the site distribution board (see more details below under ‘offset value’). Under this arrangement every kWh generated by the system would be exported, and the export rate would be paid.
The value of exported electricity can vary considerably and Renewables First have extensive expertise in negotiating the best value export price for electricity.
The exported electricity can be paid for by entering a Power Purchase Agreement, or by entering a contract with an electricity supplier as part of the Smart Export Guarantee scheme which is due to start in early .
Typically, a value of 6.5 p/kWh can be obtained using a Power Purchase Agreement, or 5.5 p/kWh using the Smart Export Guarantee scheme, although the latter scheme has not yet started.
This is where the small hydro or micro hydro system connects into the site owner’s main distribution board. It is important to remember that electricity flows like water and will always follow the easiest route to the nearest load. This means that all of the site owners loads (i.e. lighting, sockets, machinery, air conditioners etc.) that connect to the same distribution board will be supplied firstly by the hydropower system, and only once all of these loads have been satisfied will any surplus energy from the hydro system flow backwards through the incoming supply cables, either to the next nearest distribution board on the site, or out through the export meter to the grid.
Also, because the electricity produced by the hydropower system is fully grid-synchronised, it will mix seamlessly with grid-imported electricity. This mean that if the hydro system cannot meet all of the site owners loads, then all of the electricity from the hydro system will go towards the loads and any deficit will be seamlessly imported from the grid.
Equally, if the hydro system was supplying all of the local loads but then a reduction in the river flow rate caused the output to suddenly drop, then the grid would instantly supply more to make up the deficit. From a consumers point of view the source of the electricity would be unknown; it could be from the hydro system, the grid or a combination of both.
In the situation where the on-site loads far exceed what the hydropower system could produce, then all of the electricity generated by the hydro system would be consumed on site. For example, if a hydropower system with a maximum power output of 100 kW was connected to a site that had a base load (i.e. the minimum load 24/7) of 500 kW, then 100% of the energy generated by the hydro system would be consumed on site. Financially this would be a good arrangement because the price paid for importing electricity from the grid is typically 12 p/kWh (varies between 8 – 16 p/kWh depending on the import tariff), so if the amount of import can be reduced, for every kWh it is reduced by the site owner saves 12 p. If you compare this saving of 12 p/kWh to an export price of 6 p/kWh, you can see that offsetting on-site loads is worth two times more than exporting the electricity.
This is actually the most common arrangement and is basically the arrangement described above under ‘offset value’ except where the on-site loads are less than the power being produced by the hydropower system. Under this arrangement the on site loads would be supplied first, then the excess power exported.
The value would be made up of the amount of energy offset at 12 p/kWh (or whatever your import electricity price is) plus the amount of energy exported at around 6.5 p/kWh. Obviously the actual value would depend on the relative proportions, but these can be estimated at a feasibility stage based on existing electricity bills and forecast energy production from the hydro system.
Generally speaking it is best to offset imported electricity first, then export any remaining surplus to get the highest revenue from a hydropower system.
Are you interested in learning more about retaining dam? Contact us today to secure an expert consultation!
Previous: The Best Online Fabric Stores Today - Picks by Bob Vila
Next: The Ultimate Buyer's Guide for Purchasing Dry bulk storage silos
If you are interested in sending in a Guest Blogger Submission,welcome to write for us!
All Comments ( 0 )